Crew Scheduling: Create and Edit Schedules
Schedules are the crew assignments on your timeline. Each one puts a crew member, or an empty slot waiting for one, in a position on an asset for a period of time. You create them by drawing directly on the schedule, and you change them by dragging them or opening their edit window.
You can add schedules to the timeline by drawing or automating them:
- Draw unassigned schedules: Set the dates and shape of the schedule first, and decide who fills each slot later.
- Draw with crew groups: Fill each schedule with the crew from the asset's crewing requirement as you draw. Use this to extend an existing rotation forward.
- Automate: Build repeating schedules across a date range at once from your rotations. See "Crew Scheduling: Automate the Schedule."
Before You Begin
To draw with crew groups, the asset needs a crewing requirement with its crew groups filled in. See "Crew Scheduling: Set Up Assets and Crewing Requirements."
Draw Schedules
You can draw schedules on the Personnel > Schedule > Schedule tab, on the position rows under each asset.
To draw an unassigned schedule
- Go to the Personnel > Schedule > Schedule tab.
- Make sure CREW GROUPS is turned off.
- On the position row you want to fill, click at the start date and drag to the end date, then release.
- Click SAVE.
The new schedule shows as Unassigned. To assign someone, double-click it and select a person in the Crew field, or use the Crew view to find someone available. See "Crew Scheduling: Find and Assign Crew in the Crew View."
To draw a schedule with crew groups
- Go to the Personnel > Schedule > Schedule tab.
- Click CREW GROUPS.
- Select an Asset and a Crew Group. The list shows each crew group with its crewing requirement, for example "A - Default." The window lists each position with the crew member named for it in that crew group. To use someone else for this drawing only, select a different person from the Crew list.
- Click APPLY.
- On the position row you want to fill, click at the start date and drag to the end date, then release. The schedule fills with the crew member named for that position.
- Click SAVE.
To go back to drawing unassigned schedules, click CREW GROUPS again to turn it off.
Edit Schedules
To move a schedule to a different time or row, drag the middle of it. To make it shorter or longer, drag its left or right edge.
If Disable move & resize is turned on in the general settings, dragging does nothing, and you make every change in the schedule's edit window instead.
To edit a schedule in its edit window
- Double-click the schedule on the timeline.
- Change any of the following fields:
- Crew: Search for the person by name or employee number.
- Planned Start Date and Planned End Date, each with a Time: When the schedule is planned to start and end.
- Actual Start Date and Actual End Date, each with a Time: When the schedule actually started and ended. These are usually filled in from Onboard when the crew change is completed, but you can also enter them here.
- Asset: The asset the schedule is for.
- Position Group and Position: The position being filled.
- Cost Center: The cost center used for payroll.
- Override Earning Code: An earning code to use for this schedule instead of the default.
- Travel Time Before (hrs) and Travel Time After (hrs): Hours of travel at the start and end of the schedule.
- Travel-To Instructions and Travel-From Instructions: Travel notes for the crew member.
- Click APPLY.
- Click SAVE.
NoteAPPLY closes the window, but your changes aren't saved until you click SAVE at the top right of the schedule. To remove the schedule, click DELETE in the edit window, then click SAVE.
Change the Color of Schedules
You can change the color of one or more schedules on the timeline. The paint bucket icon appears in the toolbar only when Enable Custom Colors is turned on in the general settings. See "Crew Scheduling: Set Up General Settings."
To change the color of schedules
- Go to the Personnel > Schedule > Schedule tab.
- Select the schedules you want to change:
- To select one schedule, click it.
- To select several, click the Selection Tool icon, then drag a box around the schedules.
- Click the paint bucket icon, then choose a color.
- Click SAVE.
To remove a custom color, select the schedules, click the paint bucket icon, and click CLEAR. Then click SAVE.